MOSCOW, March 11. /TASS/. Construction and installation work at power generating unit 1 of the Akkuyu nuclear power plant (NPP) under construction in Turkey has been completed, CEO of Akkuyu Nuclear, a Rosatom company, Sergey Butskikh told the Anadolu Agency.
"Having stated that construction and installation work at the first power generating unit of the power plant were completed, Butskikh noted that startup, adjustment and operation stages continue," the news agency said.
Construction of marine waterworks is completed by 95%, the chief executive said. "It means that these systems will be commissioned in the near time and start performing the function of heat taking from the nuclear power plant," he added.