First unit of Belarusian NPP to be commissioned in April - May, Rosatom says

The pilot operation phase started on December 22, 2020 is currently underway at the first power unit of the Belarusian NPP

MOSCOW, January 26. /TASS/. The first power unit of the Belarusian Nuclear Power Plant (NPP) is scheduled for commissioning in April - May of this year, press service of ASE, the engineering division of the Russian state nuclear corporation Rosatom, told TASS on Tuesday.

The pilot operation phase started on December 22, 2020 is currently underway at the first power unit of the Belarusian NPP. This is the final and the longest testing of the power unit before commissioning.